Determine over- and under-billings for a company with the following information: Job Number: 7310 Job Name: Mountain Peak Office Remodel Current Contract Amount: $256,852 Total

Determine over- and under-billings for a company with the following information:

Job Number: 7310

Job Name: Mountain Peak Office Remodel

Current Contract Amount: $256,852

Total Estimated Cost at Completion: $225,236

Actual Costs to Date: $202,138

Total Billed: $252,253

Job Number: 8310

Job Name: East Street Restaurant

Current Contract Amount: $350,199

Total Estimated Cost at Completion: $310,564

Actual Costs to Date: $152,364

Total Billed: $178,256

Job Number: 9310

Job Name: Market Street Warehouse

Current Contract Amount: $55,123

Total Estimated Cost at Completion: $45,224

Actual Costs to Date: $5,211

Total Billed: $5,500

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Of EPAs Fiscal 2013 And 2012 Consolidated Financial Statements

Authors: U.S. Environmental Protection Agency

1st Edition

1500696218, 978-1500696214

More Books

Students also viewed these Accounting questions

Question

Define goals and plans and explain the relationship between them.

Answered: 1 week ago