Determine the critical path, total slacks for each activity and project duration for the network represented by the following table. Discuss the degree of sensitivity
Determine the critical path, total slacks for each activity and project duration for the network represented by the following table. Discuss the degree of sensitivity embodied by the network.
Activity | Predecessor | Duration (days) |
A | -- | 1 |
B | A | 30 |
C | A | 60 |
D | A | 30 |
E | D | 20 |
F | B | 45 |
G | C,F | 95 |
H | G | 50 |
I | E | 50 |
J | I | 90 |
K | H,J,L | 75 |
L | C | 155 |
M | K | 120 |
N | M | 20 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started