Determine the financial requirement for the following cost expenditure for a small remodeling job. Assumptions: The markup for this project is 10%. Finance charge is

Determine the financial requirement for the following cost expenditure for a small remodeling job. Assumptions: The markup for this project is 10%. Finance charge is 1% per month. Retainage is 5% throughout project. Payments are billed at the end of each month, and are received one month later.image text in transcribed

Month Monthly Costs (Includes direct costs and indirect costs) 2 69,000 $21,800 Month 4 Direct Cost Indirect Cost Subtotal Markup 10% Total Billed Retainage 5% Payment Received Return of Retainage Cost to Date Billed to Date Paid to Date Overdraft @ end of month Interest on overdraft balance Total Amount financed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Care And Counsel For Combat Trauma Training Program Workbook For Audit Only

Authors: Cru Military, American Association Of Christian Counselors, Light University, Karen D Watkins

1st Edition

0986363081, 978-0986363085

More Books

Students also viewed these Accounting questions

Question

What did the no Child left behind act in 2002 ensure

Answered: 1 week ago