Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problen The monthly forecasts for Product X for January, February, and March are 920,1,560, and 1,270, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning imventory is 400 units. Storage cost is $5 per unit per month based on ending inventory level, standard pay rate is $8 per hour, hiring and training cost is $110 per worker, layoff cost is $210 per worket, and worker productivity is 0.1 unit per hour. Assume that you start off with 44 workers and that they work 8 hours per day. (Leave no cells blank - be certain to enter " 0 wherever required. Input all values as positive values. Round Workers Required up to next higher whole number. Round all other variables to nearest whole number.) Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problen The monthly forecasts for Product X for January, February, and March are 920,1,560, and 1,270, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning imventory is 400 units. Storage cost is $5 per unit per month based on ending inventory level, standard pay rate is $8 per hour, hiring and training cost is $110 per worker, layoff cost is $210 per worket, and worker productivity is 0.1 unit per hour. Assume that you start off with 44 workers and that they work 8 hours per day. (Leave no cells blank - be certain to enter " 0 wherever required. Input all values as positive values. Round Workers Required up to next higher whole number. Round all other variables to nearest whole number.)