Question
1 Approved Answer
Develop a project plan integrating project management concepts and using industry standard software. (PO4) Note: The textbook contains an example project and steps to complete
- Develop a project plan integrating project management concepts and using industry standard software. (PO4)
Note: The textbook contains an example project and steps to complete the schedule at the end of Chapters 3, 7, 8 & 9. You may find it helpful to refer to or complete these exercises prior to completing this assignment. There is also a link to video tutorials in the Supplemental Resources post.
Deliverables:
- MS Project file
- MS Word file
Data File: MS Project Assignment 2022.xlsx
Instructions:
- Using the data provided in the attached MS Excel file, create the project schedule in MS Project.
- Create new project in MS Project.
- Set the title of the project to Marketing Project. Make sure you are the author. Set the start date to todays date. (Ch 3)
- Copy and paste or type in the activities as listed in the Excel file.
- Add the WBS column to the Gantt view (Ch. 7)
- Create the WBS structure by creating summary tasks (Ch 7)
- Add project summary task (Ch 3)
- Add Durations per the Excel file (Ch 8) Note: Make sure you set the duration to Weeks!
- Set the Timescale to Weeks
- Add Predecessors per the Excel file (Ch 8)
- Identify the critical path (Ch 8)
- Add resources per the Excel file. Chapter 9 covers this, but the easiest way to do this is simply to type the names in the Resource Names column.
- Using the Resource Sheet (Ch 9), add a Std. Rate and an Ovt. rate for each resource. (You choose the rates.)
- Return to the Ganttchart page.
- Use the Split View to show both the Gantt chart with critical path and resource graph or resource usage.
- Save your MS Project file.
- Using your own MS Project file, create a Word document and answer the following questions:
- Which tasks are on the critical path?
- Which resources are overloaded?
- Briefly explain two ways you might resolve the overloads.
- What is the estimated cost of your project?
- Submit both documents to the assignment link.
WBS | Activity | Immediate Predecessor | Duration in weeks | Resource |
1 | Operational definition | |||
1.1 | Research literature | 3 | Marina | |
1.2 | Identify and define terms | 1.1 | 1 | Gelly |
1.3 | Obtain approval of definition | 1.2 | 2 | Anton |
2 | Target Selection | |||
2.1 | Solicit partners for pilot | 2 | Gelly | |
2.2 | Hold brainstorming meeting | 2.1 | 2 | Marina |
2.3 | Identify characteristics of targets | 2.2, 3.1 | 1 | Gelly |
2.4 | Obtain approval of partners | 2.3, 1.2, 3.4 | 1 | Anton |
3 | Question set | |||
3.1 | Identify process group members | 2 | Anton | |
3.2 | Develop question set | 2.3 | 4 | Gelly |
3.3 | Prototype and validate question set | 3.2 | 3 | Marina |
3.4 | Add partners | 3.1, 2.1 | 3 | Marina |
4 | Pilot process | |||
4.1 | Schedule with target audience | 2.4 | 2 | Marina |
4.2 | Conduct beta test | 3.4, 2.4 | 2 | Anton |
4.3 | Process feedback from target audience | 4.2 | 2 | Gelly |
4.4 | Conduct pilot | 4.3 | 2 | Anton |
4.5 | Analyze results | 4.4 | 2 | Anton |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started