Develop an MTM-2 analysis of the right-hand activities for the cable-clamp assembly shown in Figure (4.17) Right-Hand: Gets (G): Symbol: Time: Clamp (10) RE G
- Develop an MTM-2 analysis of the right-hand activities for the cable-clamp assembly shown in Figure (4.17)
Right-Hand:
Gets (G): Symbol: Time:
Clamp (10) RE G 1.00
First nut (9) RE G 1.00
Second nut (9) RE G 1.00
Place (P):
Cable clamp (10) M P RL 1.20
First nut (9) M P 1.20
Second nut (9) M P 1.20
Hold (H):
U-bolt (10) H 11.00
Run (R):
Down 1st nut U RL 3.40
Down 2nd nut U RL 3.40
Wait (W): UD 0.90