Question

1 Approved Answer

Develop the MRP for eight weeks of the next explosion of materials and accompanying data; INVENTORY REGISTER ELEMENTS B C D Time of delivery 1

Develop the MRP for eight weeks of the next explosion of materials and accompanying data;

image text in transcribed

INVENTORY REGISTER

ELEMENTS

B

C

D

Time of delivery

1 week

2 week

1 week

Inicial inventory

550

0

500

purchase policy

POQ ( P = 2 )

L x L

FOQ (100)

security inventory

100

100

Pending to recieve (units)

500 ( S - 1)

650 ( S - 1)

The master production schedule for product A requires the production department to deliver the product according to the following sales schedule: 200 units in week 4, 175 units in week 5, 170 units in week 6, 200 units in week 7 and 150 units during week 8. Develop the MRP that covers the following eight weeks, also pointing out any notice of action that may be necessary if products are not currently in stock and the production of the product requires two weeks delivery time, the safety inventory of the Product is 100 units and the warehouse manager informs you that in Week two a shipment of 150 units of that product is expected, which was erroneously sent to the marketer

A B 2 2 D 2 D 2 A B 2 2 D 2 D 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions