Question
)Developing the case of the Sustainability Case Competition 1.1 agree a theme or topic 5 days 1.2 draft case 10 days 1.3 test and update
)Developing the case
of the Sustainability Case Competition
1.1
agree a theme or topic
5 days
1.2
draft case
10 days
1.3
test and update each stage of the draft case
10 days
1.4
develop a rule book and print
5 days
1.5 needed to be agreed on, which would probably take about fdays
a draft case needed to be written, which would take at least ten days
+ The draft case would then need to be tested and updated, which would take about
another five days for each stage.
a rule book would need to be developed
case five days for printing books
Developing the rule book could technically start at the same time as the case was drafted,
whereas writing the draft, testing, and updating the case would have to be done in sequential
order. Clearly, both the rule book and updating of the case would have to be completed before
they could be sent to printing
and the
case would need to be printed. Wilson estimated that developing the rule book would not take
more than ten days and, to be on the safe side, Brown should allow up to
The communications and marketing department
2)
Set up
room and prize for the event
2.1 Finding available rooms, placing bookings, and receiving confirmations from
the central
2 days
2.2 obtain prizes from some potential local employers of the region. included: prize money,
tuition waivers, gift cards, or perhaps
3)
promotional activities for the event
( start after
3.1 develop social media content 5 days
3.2 set up a website for the event 10 days
3.3
set up the online registration system 10 days
3.4
promote the event by
class
visits 10 days
3.5 photographer to capture the event. 2 days
using the school website, social media
he promotional activities
staff in the communications and marketing department. They would probably need about
5 days to develop social media content
10 days to set up a website for the event, and
Next 10 days to set up the online registration system.
Regarding class visits, the faculty member working
with Brown would need up to 10 days to promote the event.
While social media content and the
website could be developed as soon as the draft case was produced and the competition date
was
confirmed, class visits should not start before the date was confirmed and the rule book was
completed in order to be able to answer any student questions about details, such as how their
contribution would be judged, what support materials they could use, and so on.
he promotional activities
Brown also suggested booking a photographer to capture
the event. This could be done right after the venue was secured and would take no more than 2
days to complete.
Brown about 2 days to produce
4)
m
ake
list of potential panel members
4.1 produce names of potential panel members 2 days
4.2
Inviting potential panelists, including awaiting their responses 15 days
Inviting potential panelists, including awaiting their responses, would take Brown another 15
days to complete.
5)
Activities after closing the project
5.1
send thank-you notes, post a story on the school's own social media channels, and make
notes for improvements. 1 day
5.2
update the budget with actual costs 5 days
5.3
closing the project and housekeeping items 2 days
send thank-you notes, post a story on the school's own social media channels, and make notes
for improvements. 1 day
5 days additional days to update the budget with actual costs
2 days would be necessary for
These are pointers from the case study. How can I calculate the estimate duration and predecessors from this information?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started