Development of Version 2.0 of a particular accounting software product is being considered by Jose Nogueras technology firm in Baton Rouge. The activities necessary for
Development of Version 2.0 of a particular accounting software product is being considered by Jose Nogueras technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost | Immediate Predecessor(s) |
A | 4 | 3 | $2,000 | $2,600 | - |
B | 2 | 1 | $2,200 | $2,800 | - |
C | 4 | 3 | $500 | $800 | - |
D | 8 | 5 | $2,300 | $2,600 | A, B |
E | 6 | 3 | $900 | $1,200 | C |
F | 3 | 2 | $3,000 | $4,200 | D, E |
G | 4 | 2 | $1,400 | $2,000 | E, F |
a. What is the critical path [ Select ] ["C, E, G", "C, E, F, G", "B, D, F, G", "B, F, E, G", "A, D, F, G"]
b. What is the project length? [ Select ] ["22 weeks", "14 weeks", "34 weeks", "19 weeks", "17 weeks"]
c. If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost? [ Select ] ["D, & E, $100", "D, $100.00", "C, $50", "E, $100", "G, $300"]
d. If you wish to take another week off the project, which activity would you choose and what is the total cumulative cost? [ Select ] ["D, $100", "D, $200", "E, $100", "G, $75", "E, $300"]
e. What is the maximum time that can be crashed? [ Select ] ["10 weeks", "7 weeks", "12 weeks", "5 weeks", "9 weeks"] . How much would costs increase? $ [ Select ] ["$1,900", "$2,900", "$2,700", "$3,300", "$1,850"]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started