Question
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Total Cost with Crashing | Immediate Predecessor(s) |
A | 4 | 3 | $2,100 | $2,700 | |
B | 2 | 1 | $2,300 | $3,000 | |
C | 3 | 3 | $500 | $500 | |
D | 8 | 4 | $2,500 | $2,820 | A |
E | 6 | 3 | $1,000 | $1,375 | B |
F | 3 | 2 | $3,200 | $4,400 | C |
G | 4 | 2 | $1,500 | $2,000 | D, E |
a) Based on the given information regarding the activities for the project, the project length = ____weeks.
b) The total cost required for completing this project on normal time = ______
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
A
B
C
D
E
F
G
.
The cost of the project based on the first activity selected for crashing will increase by
$nothing.
d) The maximum weeks by which the project can be reduced by crashing =
7
8
9
10
11
12
weeks.
Total cost of crashing the project to minimum (or maximum weeks possible) =
$nothing.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started