Diego is the project manager at an Entertainment company and in his Schedule Plan for his concert in 2021, he had to note that Outdoor
Diego is the project manager at an Entertainment company and in his Schedule Plan for his concert in 2021, he had to note that Outdoor concerts can only be scheduled once the government of Ontario lifts the lockdown measures on outdoor events. What kind of Dependency describes the above situation? Organizational dependency Discretionary dependency External dependency Internal dependency