Question

1 Approved Answer

Direct costs of a project are shown on the following bar chart (see Table P6.2). Assume -> $500 per month indirect cost and 10% retainage

Direct costs of a project are shown on the following bar chart (see Table P6.2).

Assume -> $500 per month indirect cost and 10% retainage with payment time lag of one month.

Calculate the projects net cash flow for a 10-percent markup.

Estimate the proper markup for 1%, 1.5%, and 2% rate of return per month

image text in transcribed

TABLE P6.2 Project Bar Chart Activity Month 3 1 2 4 $2,000 $1,200 $3,000 1. Survey 2. Mobilization 3. Trench 4. Lay pipe 5. Concrete 6. Backfill 7. Move out $6,000 $3,000 $3.00 $500 $500 $500 $500 $1,000 8. Prepare valves 9. Install valves $1,000 10. Test $1,500 TABLE P6.2 Project Bar Chart Activity Month 3 1 2 4 $2,000 $1,200 $3,000 1. Survey 2. Mobilization 3. Trench 4. Lay pipe 5. Concrete 6. Backfill 7. Move out $6,000 $3,000 $3.00 $500 $500 $500 $500 $1,000 8. Prepare valves 9. Install valves $1,000 10. Test $1,500

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Proli Footwear Inc An Audit And Fraud Simulation For Team-Based Student Learning

Authors: Patricia Poli, Richard Proctor

2nd Edition

0615455492, 978-0615455495

More Books

Students also viewed these Accounting questions