Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Direct Labor Variances La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of

Direct Labor Variances

La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:

Quantity of direct labor used 450 hrs.
Actual rate for direct labor $13.00 per hr.
Bicycles completed in July 210
Standard direct labor per bicycle 2 hrs.
Standard rate for direct labor $13.30 per hr.

a. Determine the direct labor rate variance, time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Rate variance $ Favorable
Time variance $ Unfavorable
Total direct labor cost variance $ Unfavorable

b. How much direct labor should be debited to Work in Process? $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Efficient Auditing Of Private Companies A Guide To Audit Planning Implementation And Control

Authors: The Institute Of Chartered Accountants

1st Edition

1841400432, 978-1841400433

More Books

Students also viewed these Accounting questions

Question

What is the purpose of a research report?

Answered: 1 week ago

Question

b. Explain how you initially felt about the communication.

Answered: 1 week ago

Question

3. Identify the methods used within each of the three approaches.

Answered: 1 week ago

Question

a. When did your ancestors come to the United States?

Answered: 1 week ago