Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 units of product were as follows:

Standard Costs Actual Costs
Direct materials 9,400 lb. at $5.80 9,300 lb. at $5.70
Direct labor 1,800 hrs. at $16.40 1,840 hrs. at $16.70
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 1,880 direct
labor hrs.:
Variable cost, $4.00 $7,130 variable cost
Fixed cost, $6.30 $11,844 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct materials price variance $fill in the blank 1 Favorable

Incorrect

Direct materials quantity variance fill in the blank 3 Favorable
Total direct materials cost variance $fill in the blank 5 Favorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct labor rate variance $fill in the blank 7 Unfavorable
Direct labor time variance fill in the blank 9 Unfavorable
Total direct labor cost variance $fill in the blank 11 Unfavorable

c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $fill in the blank 13 Favorable
Fixed factory overhead volume variance fill in the blank 15 Unfavorable
Total factory overhead cost variance $fill in the blank 17 Unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions