Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Eastern Polymers, Inc., processes a base chemical into plastic. Standard costs and actual costs for

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

Eastern Polymers, Inc., processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 5,600 units of product were as follows:

Standard Costs Actual Costs
Direct materials 7,300 lbs. at $5.00 7,200 lbs. at $4.90
Direct labor 1,400 hrs. at $17.70 1,430 hrs. at $18.10
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 1,460 direct
labor hrs.:
Variable cost, $3.50 $4,850 variable cost
Fixed cost, $5.50 $8,030 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Price variance $ Favorable or Unfavorable
Quantity variance $ Favorable or Unfavorable
Total direct materials cost variance $ Favorable or Unfavorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Rate variance $ Favorable or Unfavorable
Time variance $ Favorable or Unfavorable
Total direct labor cost variance $ Favorable or Unfavorable

c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $ Favorable or Unfavorable
Fixed factory overhead volume variance $ Favorable or Unfavorable
Total factory overhead cost variance $ Favorable or Unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Explain the importance of Human Resource Management

Answered: 1 week ago

Question

Discuss the scope of Human Resource Management

Answered: 1 week ago

Question

Discuss the different types of leadership

Answered: 1 week ago

Question

Write a note on Organisation manuals

Answered: 1 week ago