Question
Discussion Assignments: Project Scheduling Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas
Discussion Assignments:
Project Scheduling
Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:
Create a testing plan
Once the testing plan is ready, your team can:
Test the user interfaces
Test the database
Test the network
Write the documentation first draft
When the user interface tests are complete, you can:
Perform user testingenlist some users to test the user interface
When the database and network testing are complete, you can:
Perform integration testingnetwork with the database
When the user testing of the user interface and the database testing are complete, you can:
Perform integration testingdatabase, network, and user interface
When all integration testing and user testing are complete, you can:
Perform system testing
Then you can:
Review and revise documentation
After all other tasks are complete, you can:
Obtain management approval
Duration estimates for the tasks:
a. 3 days
b. 10 days
c. 6 days
d. 7 days
e. 20 days
f. 5 days
g. 3 days
h. 2 days
i. 8 days
j. 4 days
k. 5 days
1. Create a network diagram and a Gantt chart for the project tasks. Ask your instructor if you are permitted to use software such as Microsoft Project to help you prepare your diagrams.
a. What is the planned duration of the testing project?
b. What is the critical path for the testing project?
c. For each task NOT on the critical path, calculate the amount of slack available.
d. If the user testing of the user interface takes 15 days, what will the impact be on the project duration?
2. Go online and find at least two sites with definitions of fast-tracking and crashing a project schedule.
a. Prepare proper reference citations for the sites you located, using APA style.
b. In your own words, write definitions for project fast tracking and project crashing.
c. Consider the plan you prepared for the software system testing project in question 1 above. If you were informed by management that you must reduce the planned duration of the project by five days, describe how you, as a project manager, could crash or fast-trackthis project. Be specific in identifying exactly what could be changed in the project plan for each option.
d. If the request to speed up the project occurs after day 25 of the original schedule, what is the only option available?
3. Go online and research the difference between total slack and free slack.
a. Prepare proper reference citations for the sites you located, using APA style.
b. Write definitions of total slack and free slack in your own words.
c. Why would the distinction between different forms of slack be important to a project manager?
Budget Planning:
1. Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods indicated. Show your work.
Note that members of the bridal party are already counted as guests, you dont need to add them twice.
a. Parametric estimate
b. Bottom-up estimate
c. Analogous cost estimate
d. You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?
e. Your mother points out you should probably have valet parking, which will cost $500. Which estimate(s) will change?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started