Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Do a What-If analysis where you set the break-even for the project, NPV = 0, based on the levels of three key parameters: the tax

Do a What-If analysis where you set the break-even for the project, NPV = 0, based on the levels of three key parameters: the tax credit (cell B19), the SIP rate (cell B14) and Electricity Cost (Cell B21). For example, Goal Seek will tell you the tax credit percentage that would make the NPV = 0.

image text in transcribedimage text in transcribed

In the cells below the "Assumptions for Case" are formulas for key variables in column B starting with B35 and rows 71 - 74. Do not modify these cells. You are to enter the formulas only in the cells that are shaded: Assumptions for Case: Size, kW cost per kW Efficiency rating annual degradation 15 kW $7,000 $ per kW 18% % Total cost $ end-of-life salva value to deprecia $ 105,000.00 15% 89,250.00 0.50% % SIP rate system rating design factor $1.95 per W 12585 W 0.9 tax rate tax credit 38% of profits 30% of system cost Notes: 1) Electricity generation for year 1 is in cell B36 based on a formula in that cell. For each succeeding year electricity generation declines by 0.5%, as stated in the case. 2) The hurdle rate or discount rate is in cell B30 and is based on an after-tax rate, since all of the -, cash flows are adjusted for taxes. 3) The formula for the Solar Incentive Program (SIP) is in cell B64. 4) Total cash flow for the payback method is the formula in cell B71. 5) Number of years for payback is in cell B74. 6) Initially assume straight line depreciation over 5 years; in question 3) you will use accelerated depreciation based on MACRS. Electricity cost annual increase $0.17 per kWh 3% maintainance annual increase $15 per kW 2% insurance annual increase 0.30% of total cost 2% hurdle rate 3.53% year 2 3 4 5 6 7 8 9 10 11 1 $0.17 electricity cost electricity generation kW electricity cost savings 23652 $4,020.84 $15 maintainance cost per kW total maint cost (based on 15kW) insurance cost total insurance 0.30% 315.00 $ $3,705.84 total cost savings tax on cost savings 39 40 maintainance cost per kW $15 41 total maint cost (based on 15kW) 42 43 insurance cost 0.30% 44 total insurance $ 315.00 45 46 47 48 total cost savings $3,705.84 49 tax on cost savings 50 51 Depreciation 52 Tax savings from depreciation 53 54 Net savings $3,705.84 55 56 NPV of net savings (304) 57 NPV of net savings (127) 58 59 Tax incentive $ 31,500.00 60 61 NPVw tax incentive, 30y 62 NPV w tax incentive, 12y 63 64 SIP $22,086.68 65 Tax on SIP 66 Net SIP 67 68 NPVw tax inc and SIP, 30y $ 69 NPV w tax ino and SIP, 12y $ 70 71 Total CF for payback on proje ($47,707.49) 72 with both tax incentive and SIP 73 Cumulative CF $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 1547 ($47,707.49) ($47,707.49) ($47,707.49) ($47,707.49) ($47,707.49) ######### ######### ######### ################## ######### ######### ######### ######### ######### ######### ######### ######### ######### ######### ######### ######### In the cells below the "Assumptions for Case" are formulas for key variables in column B starting with B35 and rows 71 - 74. Do not modify these cells. You are to enter the formulas only in the cells that are shaded: Assumptions for Case: Size, kW cost per kW Efficiency rating annual degradation 15 kW $7,000 $ per kW 18% % Total cost $ end-of-life salva value to deprecia $ 105,000.00 15% 89,250.00 0.50% % SIP rate system rating design factor $1.95 per W 12585 W 0.9 tax rate tax credit 38% of profits 30% of system cost Notes: 1) Electricity generation for year 1 is in cell B36 based on a formula in that cell. For each succeeding year electricity generation declines by 0.5%, as stated in the case. 2) The hurdle rate or discount rate is in cell B30 and is based on an after-tax rate, since all of the -, cash flows are adjusted for taxes. 3) The formula for the Solar Incentive Program (SIP) is in cell B64. 4) Total cash flow for the payback method is the formula in cell B71. 5) Number of years for payback is in cell B74. 6) Initially assume straight line depreciation over 5 years; in question 3) you will use accelerated depreciation based on MACRS. Electricity cost annual increase $0.17 per kWh 3% maintainance annual increase $15 per kW 2% insurance annual increase 0.30% of total cost 2% hurdle rate 3.53% year 2 3 4 5 6 7 8 9 10 11 1 $0.17 electricity cost electricity generation kW electricity cost savings 23652 $4,020.84 $15 maintainance cost per kW total maint cost (based on 15kW) insurance cost total insurance 0.30% 315.00 $ $3,705.84 total cost savings tax on cost savings 39 40 maintainance cost per kW $15 41 total maint cost (based on 15kW) 42 43 insurance cost 0.30% 44 total insurance $ 315.00 45 46 47 48 total cost savings $3,705.84 49 tax on cost savings 50 51 Depreciation 52 Tax savings from depreciation 53 54 Net savings $3,705.84 55 56 NPV of net savings (304) 57 NPV of net savings (127) 58 59 Tax incentive $ 31,500.00 60 61 NPVw tax incentive, 30y 62 NPV w tax incentive, 12y 63 64 SIP $22,086.68 65 Tax on SIP 66 Net SIP 67 68 NPVw tax inc and SIP, 30y $ 69 NPV w tax ino and SIP, 12y $ 70 71 Total CF for payback on proje ($47,707.49) 72 with both tax incentive and SIP 73 Cumulative CF $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 1547 ($47,707.49) ($47,707.49) ($47,707.49) ($47,707.49) ($47,707.49) ######### ######### ######### ################## ######### ######### ######### ######### ######### ######### ######### ######### ######### ######### ######### #########

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Textbook For Students And Researchers

Authors: Mukhiddin Kalonov

1st Edition

6206174077, 978-6206174073

More Books

Students also viewed these Accounting questions

Question

You can access templates and open a new workbook with this tool

Answered: 1 week ago

Question

25.0 m C B A 52.0 m 65.0 m

Answered: 1 week ago

Question

10-9 How have social technologies changed e-commerce?

Answered: 1 week ago