Do an MPS table based on the following information: Week 1 2 3 4 Forecast 100 100 100 100 Orders 120 80 50 20 Beginning
Do an MPS table based on the following information:
Week
1
2
3
4
Forecast
100
100
100
100
Orders
120
80
50
20
Beginning inventory: 0
Schedule production whenever projected-on-hand becomes negative.
Production lot size is 150 units.