Answered step by step
Verified Expert Solution
Link Copied!
Question
1 Approved Answer

do not provide answer from other postings This question is based on the case study entitled The Blue Spider project, which appears below. After the

do not provide answer from other postings

This question is based on the case study entitled "The Blue Spider project", which appears below.

After the final testing and the programmereport werecompleted, Henry Gable decided to look back on the project and contemplate its successes and challenges. In retrospect he could identify a number of challenges that emerged during the Blue Spider project life cycle, but which could not be clearly seen at the time. They caused problems that needed to be solved, and included issues such as the project manager's qualifications, the authority of a project manager, the functional employees of the customer, contractor communication and the project management system. Henry realized that Parks Corporation (PC) needed professional help if it wanted to take on future projects like the Blue Spider project and even bigger projects successfully. He raised the matter with the vice-president, Ms Esther Mokonyane, and convinced her to appoint Luthando, Prinsloo & Gopal (Pty) Ltd, an executive project management company, to render professional assistance in this regard. Luthando, Prinsloo & Gopal (Pty) Ltd would analyze Park Corporation's experience with the Blue Spider project and assist the company in re organizing for the future. The aim would be to turn PC into a modern, mature, project-oriented organization (POO)

As a senior partner of Luthando, Prinsloo & Gopal (Pty) Ltd, you have been formally approached by PC to work closely with Henry Gable and to present the following to the senior executives of PC within 40 working days

(a) How the Blue Spider project could have been approached at strategic level (45%)

CASE STUDY: THE BLUE SPIDER PROJECT

"This is impossible! Just totally impossible! Ten months ago I was sitting on top of the world. Upper-level management considered me one of the best, if not the best engineer in the plant. Now look at me! I have bags under my eyes, I haven't slept soundly in the last six months, and here I am, cleaning out my desk. I'm sure glad they gave me back my old job in engineering. I guess I could have saved myself a lot of grief and aggravation had I not accepted the promotion to project manager."

History

Gary Anderson had accepted a position with Parks Corporation right out of college. With a PhD in mechanical engineering, Gary was ready to solve the world's most traumatic problems. At first, Parks Corporation offered Gary little opportunity to do pure research, which he eagerly wanted to undertake. However, things soon changed. Parks grew into a major electronics and structural design corporation during the big boom of the late fifties and early sixties when the Department of Defence (DoD) contracts were plentiful.

Parks Corporation grew from a handful of engineers to a major DoD contractor, employing some 6,500 people. During the recession of the late sixties, money became scarce and major layoffs resulted in lowering the employment level to 2,200 employees. At that time, Parks decided to get out of the RD business and compete as a low-cost production facility while maintaining ane engineering organisation solely to support production requirements.

After attempts at virtually every project management organisational structure, Parks Corporation selected the matrix form. Each project had a program manager who reported to the director of program management. Each project also maintained an assistant project manager, normally a project engineer, who reported directly to the project manager and indirectly to the director of engineering. Program managers spent most of their time worrying about cost and time, whereas the assistant program managers worried more about technical performance.

With the poor job market for engineers, Gary and his colleagues began taking coursework towards an MBA degree, should the job market deteriorate further.

In 1975, with the upturn in DoD spending, Parks had to change its corporate strategy. Parks had spent the last seven years bidding on the production phase of large programs. But now, with the new evaluation criteria set forth for contract award, those companies winning the R&D and qualification phases had a definite edge on being awarded the production contract. The production contract was where the big profits could be found. In keeping with this new strategy, Parks began to beef up its R&D engineering staff. By 1978, Parks had increased in size to 2,700 employees. The increase was mostly in engineering. Experienced R&D personnel were difficult to find for the salaries that Parks was offering. Parks was, however, able to lure some employees away from the competitors, but relied mostly upon the younger, inexperienced engineers fresh out of college.

With the adoption of this corporate strategy, Parks Corporation administered a new wage and salary program that included job upgrading. Gary was promoted to senior scientist, responsible for all R&D activities performed in the mechanical engineering department. Gary had distinguished himself as an outstanding production engineer during the past several years, and management felt that his contribution could be extended to R&D as well.

In January 1978, Parks Corporation decided to compete for Phase I of the Blue Spider Project, an R&D effort that, if successful, could lead into a $500 million program spread out over twenty years. The Blue Spider Project was an attempt to improve the structural capabilities of the Spartan Missile, a short-range tactical missile used by the Army. The Spartan Missile was exhibiting fatigue failure after six years in the field. This was three years less than what the original design specifications called for. The Army wanted new materials that could result in a longer life for the Spartan Missile.

Lord Industries was the prime contractor for the Army's Spartan Program. Parks Corporation would be a subcontractor to Lord if they could successfully bid and win the project. The criteria for subcontractor selection were based not only on low bid, but also on technical expertise as well as management performance on other projects. Parks' management felt that they had a distinct advantage over most of the other competitors because they had successfully worked on other projects for Lord Industries.

The Blue Spider Project Kick-off

On November 3, 1977, Henry Gable, the director of engineering, called Gary Anderson into his office.

Henry Gable: "Gary, I've just been notified through the grapevine that Lord will be issuing the RFP for the Blue Spider Project by the end of this month, with a thirty-day response period. I've been waiting a long time for a project like this to come along so that I can experiment with some new ideas that I have. This project is going to be my baby all the way! I want you to head up the proposal team. I think it must be an engineer. I'll make sure that you get a good proposal manager to help you. If we start work now, we can get close to two months of research in before proposal submittal. That will give us a one-month's edge on our competitors."

Gary was pleased to be involved in such an effort. He had absolutely no trouble in getting functional support for the R&D effort necessary to put together a technical proposal. All of the functional managers continually remarked to Gary that, "This must be a biggy. The director of engineering has thrown all of his support behind you."

On December 2, the RFP was received. The only problem area that Gary could see was that the technical specifications stated that all components must be able to operate normally and successfully through a temperature range of -65 to 145F. Current testing indicated the Parks Corporation's design would not function above 130F. An intensive R&D effort was conducted over the next three weeks. Everywhere Gary looked, it appeared that the entire organisation was working on his technical proposal.

A week before the final proposal was to be submitted, Gary and Henry Gable met to develop a company position concerning the inability of the preliminary design material to be operated above 130F.

Gary Anderson: "Henry, I don't think it is going to be possible to meet specification requirements unless we change our design material or incorporate new materials. Everything I've tried indicates we're in trouble."

Henry Gable: "We're in trouble only if the customer knows about it. Let the proposal state that we expect our design to be operative up to 155F. That'll please the customer."

Gary Anderson: "That seems unethical to me. Why don't we just tell them the truth?"

Henry Gable: "The truth doesn't always win proposals. I picked you to head up this effort because I thought that you'd understand. I could have just as easily selected one of our many moral project managers. I'm considering you for program manager after we win the program. If you're going to pull this conscientious issue on me like the other project managers do, I'll find someone else. Look at it this way; later we can convince the customer to change the specifications. After all, we'll be so far downstream that they will have no choice."

After two solid months of sixteen-hour days, the proposal was submitted. On February 10, 1978 Lord Industries announced that Parks Corporation would be awarded the Blue Spider Project. The contract called for a ten-month effort, negotiated at $2.2 million at a firm-fixed price.

Selecting the Project Manager

Following contract award, Henry Gable called Gary in for a conference.

Henry Gable: "Congratulations Gary! You did a fine job. The Blue Spider Project has great potential for ongoing business over the next ten years, provided that we perform well during the R&D phase. Obviously you're the most qualified person in the plant to head up the project. How would you feel about a transfer to program management?"

Gary: "I think it would be a real challenge. I could make maximum use of the MBA degree I earned last year. I've always wanted to be in program management."

Henry Gable: "Having several master's degrees, or even doctorate's for that matter, does not guarantee that you'll be a successful project manager. There are three requirements for effective program management: you must be able to communicate both in writing and orally; you must know how to motivate people; and you must be willing to give up your car pool. The last one is extremely important in that program managers must be totally committed and dedicated to the program, regardless of how much time is involved.

"But this is not the reason why I asked you to come here. Going from project engineering to program management is a big step. There are only two places you can go from program management; up the organisation or out the door. I know of very, very few engineers that failed in program management and were permitted to return."

Gary: "Why is that? If I'm considered to be the best engineer in the plant, why can't I return to engineering?"

Henry Gable: "Program management is a world of its own. It has its own formal and informal organisational ties. Program managers are outsiders. You'll find out. You might not be able to keep the strong personal ties you now have with your fellow employees. You'll have to force even your best friends to comply with your standards. Program managers can go from program to program, but functional departments remain intact."

"I'm telling you all this for a reason. We've worked well together the past several years. But if I sign the release so that you can work for Grey in Program Management, you'll be on your own, like hiring into a new company. I've already signed the release. You still have some time to think about it."

Gary: "One thing I don't understand. With all of the good program managers we have here, why am I given this opportunity?"

Henry Gable: "Almost all of our program managers are over forty-five years old. This resulted from our massive layoffs several years ago when we were forced to lay off the younger, inexperienced program managers. You were selected because of your age and because all of our other program managers have worked on only production-type programs. We need someone at the reigns who knows R&D. Your counterpart at Lord Industries will be an R&D type. You have to fight fire with fire."

"I have an ulterior reason for wanting you to accept this position. Because of the division of authority between program management, who can I communicate with concerning R&D work? The program managers we have now are interested only in time and cost. We need a manager who will bend over backwards to get performance also. I think you're that man. You know the commitment we made to Lord when we submitted that proposal. You have to try to achieve that. Remember, this program is my baby. You'll get all the support you need. I'm tied up on another project now. But when it's over, I'll be following your work like a hawk. We'll have to get together occasionally and discuss new techniques.

"Take a day or two to think it over. If you want the position, make an appointment to see Elliot Grey, the director of program management. He'll give you the same speech I did. I'll assign Paul Evans to you as chief project engineer. He's a seasoned veteran and you should have no trouble working with him. He'll give you good advice. He's a good man."

The Work Begins

Gary accepted the new challenge. His first major hurdle occurred in staffing the project. The top priority given to him to bid the program did not follow through for staffing. The survival of Parks Corporation depended upon the profits received from the production programs. In keeping with this philosophy Gary found that engineering managers (even his former boss) were reluctant to give up their key people to the Blue Spider Program. However, with a little support from Henry Gable, Gary formed an adequate staff for the program.

Right from the start Gary was worried that the test matrix called out in the technical volume of the proposal would not produce results that could satisfy specifications. Gary had a milestone, ninety days after go-ahead, to identify the raw materials that could satisfy specification requirements. Gary and Paul Evans held a meeting to map out their strategy for the first few months.

Gary Anderson: "Well Paul, we're starting out with our backs against the wall on this one. Any recommendations?"

Paul Evans: "I also have my doubts in the validity of this test matrix. Fortunately, I've been through this before. Gable thinks this is his project and he'll sure as hell try to manipulate us. I have to report to him every morning at 7:30 a.m. with the raw data results of the previous day's testing. He wants to see it before you do. He also stated that he wants to meet with me alone.

"Lord will be the big program. If the test matrix proves to be a failure, we're going to have to change the scope of effort. Remember, this is an FFP contract. If we change the scope of work and do additional work in the earlier phases of the program, then we should prepare a trade-off analysis to see what we can delete downstream so as to not overrun the budget."

Gary Anderson: "I'm going to let the other project office personnel handle the administration work. You and I are going to live in the research labs until we get some results. We'll let the other project office personnel run the weekly team meetings."

For the next three weeks Gary and Paul spent virtually twelve hours per day, seven days a week, in the research and development lab. None of the results showed any promise. Gary kept trying to set up a meeting with Henry Gable but always found him unavailable.

During the fourth week, Gary, Paul and the key functional department managers met to develop an alternate test matrix. The new test matrix looked good. Gary and his team worked frantically to develop a new workable schedule that would not have an impact on the second milestone, which was to occur at the end of 180 days. The second milestone was the final acceptance of the raw materials and preparation of production runs of the raw materials to verify that there would be no scale-up differences between lab development and full-scale production.

Gary personally prepared all of the technical handouts for the interchange meeting. After all, he would be the one presenting all of the data. The technical interchange meeting was scheduled for two days. On the first day, Gary presented all of the data, including test results, and the next day the test matrix. The customer appeared displeased with the progress to date and decided to have their own in-house caucus that evening to go over the material that was presented.

The following morning the customer stated their position: "First of all, Gary, we're quite pleased to have a project manager who has such a command of technology. That's good. But every time we've tried to contact you last month, you were unavailable or had to be paged in the research laboratories. You did an acceptable job presenting the technical data, but your project office personnel presented the administrative data. We, at Lord, do not think that you're maintaining the proper balance between your technical and administrative responsibilities. We prefer that you personally give the administrative data and your chief project engineer present the technical data.

"We did not receive any agenda. Our people like to know what will be discussed, and when. We also want a copy of all handouts to be presented at least three days in advance. We need time to scrutinize the data. You can't expect us to walk in here blind and make decisions after seeing the data for ten minutes.

"To be frank, we feel that the data to date are totally unacceptable. If the data do not improve, we will have no choice but to issue a stop work order and look for a new contractor. The new test matrix looks good, especially since this is a firm-fixed-price contract. Your company will bear the burden for all costs for the additional work. A trade-off with later work may be possible, but this will depend upon the results presented at the second design review meeting, ninety days from now.

"We have decided to establish a customer office at Parks to follow your work more closely. Our people feel that monthly meetings are insufficient during R&D activities. We would like our customer representative to have daily verbal meetings with you or your staff. He will then keep us posted. Obviously, we had expected to review much more experimental data than you have given us.

"Many of our top quality engineers would like to talk directly to your engineering community, without having to continually waste time by having to go through the project office. We must insist upon this last point. Remember, your effort may be only $2.2 million, but our total package is $100 million. We have a lot more at stake than you people do. Our engineers do not like to get information that has been filtered by the project office. They want to help you.

"And last, don't forget that you people have a contractual requirement to prepare complete minutes for all interchange meetings. Send us the original for signature before going to publication.

Although Gary was unhappy with the first team meeting, especially with the requests made by Lord Industries, he felt that they had sufficient justification for their comments. Following the team meeting, Gary personally prepared the complete minutes. "This is absurd," thought Gary. "I've wasted almost one entire week doing nothing more than administrative paperwork. Why do we need such detailed minutes? Can't a rough summary just as well suffice? Why is it that customers want everything documented? That's like an indication of fear. We've been completely cooperative with them. There has been no hostility between us. If we've gotten this much paperwork to do now, I hate to imagine what it will be like if we get into trouble."

A New Role

Gary completed and distributed the minutes to the customer as well as to all key team members.

For the next five weeks testing went according to plan, or at least Gary thought that it had. The results were still poor. Gary was so caught up in administrative paperwork that he hadn't found time to visit the research labs in over a month. On a Wednesday morning, Gary entered the lab to observe the morning testing. Upon arriving in the lab, Gary found Paul Evans, Henry Gable, and two technicians testing a new material, JXB-3.

Henry Gable: "Gary, your problems will soon be over. This new material, JXB-3, will permit you to satisfy specification requirements. Paul and I have been testing it for two weeks. We wanted to let you know, but were afraid that if the word leaked out to the customer that we were spending their money for testing materials that were not called out in the program plan, then they would probably go crazy and might cancel the contract. Look at these results. They're super!"

Gary Anderson: "Am I supposed to be the one to tell the customer now? This could cause a big wave."

Henry Gable: "There won't be any wave. Just tell them that we did it with our own R&D funds. That'll please them because they'll think we're spending our own money to support their program."

Before presenting the information to Lord, Gary called a team meeting to present the new data to the project personnel. At the team meeting, one functional manager spoke out: "This is a hell of a way to run a program. I like to be kept informed about everything that's happening here at Parks. How can the project office expect to get support out of the functional departments if we're kept in the dark until the very last minute? My people have been working with the existing materials for the last two months and you're telling us that it was all for nothing. Now you're giving us a material that's so new that we have no information on it whatsoever. We're now going to have to play catch-up, and that's going to cost you plenty."

One week before the 180-day milestone meeting, Gary submitted the handout package to Lord Industries for preliminary review. An hour later the phone rang.

Customer: "We've just read your handout. Where did this new material come from? How come we were not informed that this work was going on? You know, of course, that our customer, the Army, will be at this meeting. How can we explain this to them? We're postponing the review meeting until all of our people have analysed the data and are prepared to make a decision.

"The purpose of a review or interchange meeting is to exchange information when both parties have familiarity with the topic. Normally we (Lord Industries) require almost weekly interchange meetings with our other customers because we don't trust them. We disregarded this policy with Parks Corporation based upon past working relationships. But with the new state of developments, you have forced us to revert to our previous position, since we now question Parks Corporation's integrity in communicating with us. At first we believed this was due to an inexperienced program manager. Now, we're not sure."

Gary Anderson: "I wonder if the real reason we have these interchange meetings isn't to show our people that Lord Industries doesn't trust us. You're creating a hell of a lot of work for us, you know."

Customer: "You people put yourself in this position. Now you have to live with it."

Two weeks later Lord reluctantly agreed that the new material offered the greatest promise. Three weeks later the design review meeting was held. The Army was definitely not pleased with the prime contractor's recommendation to put a new untested material into a multi-million-dollar effort.

The Communications Breakdown

During the week following the design review meeting Gary planned to make the first verification mix in order to establish final specifications for selection of the raw materials. Unfortunately, the manufacturing plans were a week behind schedule, primarily because of Gary, since he had decided to reduce costs by accepting the responsibility for developing the bill of materials himself. A meeting was called by Gary to consider rescheduling of the mix.

Gary Anderson: "As you know we're about a week to ten days behind schedule. We'll have to reschedule the verification mix for late next week."

Production Manager: "Our resources are committed until a month from now. You can't expect to simply call a meeting and have everything reshuffled for the Blue Spider Program. We should have been notified earlier. Engineering has the responsibility for preparing the bill of materials. Why aren't they ready?"

Engineering Integration: "We were never asked to prepare the bill of materials. But I'm sure that we could get it out if we work our people overtime for the next two days."

Gary: "When can we remake the mix?"

Production Manager: "We have to redo at least 500 sheets of paper every time we reschedule mixes. Not only that, we have to reschedule people on all three shifts. If we are to reschedule your mix, it will have to be performed on overtime. That's going to increase your costs. If that's agreeable with you, we'll try it. But this will be the first and last time that production will bail you out. There are procedures that have to be followed."

Testing Engineer: "I've been coming to these meetings since we kicked off this program. I think I speak for the entire engineering division when I say that the role that the director of engineering is playing in this program is suppressing individuality among our highly competent personnel. In new projects, especially those involving R&D, our people are not apt to stick their necks out. Now our people are becoming ostriches. If they're prevented from contributing, even in their own slight way, then you'll probably lose them before the project gets completed. Right now I feel that I'm wasting my time here. All I need are minutes of the team meetings and I'll be happy. Then I won't have to come to these pretend meetings anymore."

The purpose for the verification mix was to make a full-scale production run of the material to verify that there would be no material property changes in scale-up from the small mixes made in the R&D laboratories. After testing, it became obvious that the wrong lots of raw materials were used in the production verification mix.

Lord Industries called a meeting for an explanation of why the mistake had occurred and what the alternatives were.

Lord: "Why did the problem occur?"

Gary: "Well, we had a problem with the bill of materials. The result was that the mix had to be made on overtime. And when you work people on overtime, you have to be willing to accept mistakes as being a way of a life. The energy cycles of our people are slow during the overtime hours."

Lord: "The ultimate responsibility has to be with you, the program manager. We, at Lord, think that you're spending too much time doing and not enough time managing. As the prime contractor, we have a hell-of-a-lot more at stake than you do. From now on we want documented weekly technical interchange meetings and closer interaction by our quality control section with yours."

Gary: "These additional team meetings are going to tie up our key people. I can't spare people to prepare handouts for weekly meetings with your people.

Lord: "Team meetings are a management responsibility. If Parks does not want the Blue Spider Program, I'm sure we can find another subcontractor. All you (Gary) have to do is to give up taking the material vendors to lunch and you'll have plenty of time for handout preparation."

Gary left the meeting feeling as though he had just gotten raked over the coals. For the next two months, Gary worked sixteen hours a day, almost everyday. Gary did not want to burden his staff with the responsibility of the handouts, so he began preparing them himself. He could have hired additional staff but with such a tight budget, and having to remake the verification mix, cost overruns appeared inevitable.

As the end of the seventh month approached, Gary was feeling pressure from within Parks Corporation. The decision-making process appeared to be slowing down and Gary found it more and more difficult to motivate his people. In fact, the grapevine was referring to the Blue Spider Project as a loser, and some of his key people acted as though they were on a sinking ship.

By the time the eighth month rolled around, the budget had nearly been expended. Gary was tired of doing everything himself. "Perhaps I should have stayed in engineering," thought Gary. Eilliot Grey and Gary Anderson had a meeting to see what could be salvaged. Grey agreed to get Gary additional corporate funding to complete the project. "But performance must be met, since there is a lot riding on the Blue Spider Project," asserted Grey. He called a team meeting to identify the program status.

Gary: "It's time to map out our strategy for the remainder of the program. Can engineering and production adhere to the schedule that I have laid out before you?"

Team Member: Engineering: "This is the first time I've seen this schedule. You can't expect me to make a decision in the next ten minutes and commit the resources of my department. We're getting a little unhappy being kept in the dark until the last minute. What happened to effective planning?"

Gary: "We still have effective planning. We must adhere to the original schedule, or at least try to adhere to it. This revised schedule will do that."

Team Member: Engineering: "Look Gary! When a project gets in trouble it is usually the functional departments that come to the rescue. But if we're kept in the dark, then how can you expect us to come to your rescue? My boss wants to know, well in advance, every decision that you're contemplating with regard to our departmental resources. Right now, we ..."

Gary: "Granted, we may have had a communications problem. But now we're in trouble and have to unite forces. What is your impression as to whether your department can meet the new schedule?"

Team Member: Engineering: "When the Blue Spider Program first got in trouble, my boss exercised his authority to make all departmental decisions regarding the program himself. I'm just a puppet. I have to check with him on everything."

Team Member: Production: "I'm in the same boat, Gary. You know we're not happy having to reschedule our facilities and people. We went through this once before. I also have to check with my boss before giving you an answer about the new schedule."

The following week the verification mix was made. Testing proceeded according to the revised schedule, and it looked as though the total schedule milestones could be met, provided that specifications could be adhered to.

Because of the revised schedule, some of the testing had to be performed on holidays. Gary wasn't pleased with asking people to work on Sundays and holidays, but had no choice, since the test matrix called for testing to be accomplished at specific times after end-of-mix.

A team meting was called on Wednesday to resolve the problem of who would work on the holiday, which would occur on Friday, as well as staffing Saturday and Sunday. During the team meeting Gary became quite disappointed. Phil Rodgers, who had been Gary's test engineering since the project started, was assigned to a new project that the grapevine called Gable's new adventure. His replacement was a relatively new man, only eight months with the company. For an hour and a half the team members argued about the little problems and continually avoided the major question, stating that they would have to first coordinate commitments with their boss. It was obvious to Gary that his team members were afraid to make major decisions and therefore "ate up" a lot of time on trivial problems.

On the following day, Thursday, Gary went to see the department manager responsible for testing, in hopes that he could use Phil Rodgers this weekend.

Department Manager: "I have specific instructions from the boss (director of engineering) to use Phil Rodgers on the new project. You'll have to see the boss if you want him back."

Gary Anderson: "But we have testing that must be accomplished this weekend. Where's the new man you assigned yesterday?"

Department Manager: "Nobody told me you had testing scheduled for this weekend. Half of my department is already on an extended weekend vacation, including Phil Rodgers and the new man. How come I'm always the last to know when we have a problem?"

Gary Anderson: "The customer is flying down their best people to observe this weekend's tests. It's too late to change anything. You and I can do the testing."

Department Manager: "Not on your life. I'm staying as far away as possible from the Blue Spider Project. I'll get you someone, but it won't be me. That's for sure!"

The weekend's testing went according to schedule. The raw data were made available to the customer under the stipulation that the final company position would be announced at the end of next month, after the functional departments had a chance to analyse it.

Final testing was completed during the second week of the ninth month. The initial results looked excellent. The materials were within contract specifications, and although they were new, both Gary and Lord's management felt that there would be little difficulty in convincing the Army that this was the way to go. Henry Gable visited Gary and congratulated him on a job well done.

All that now remained was the making of four additional full-scale verification mixes in order to determine how much deviation there would be in material properties between full-sized production-run mixes. Gary tried to get the customer to concur (as part of the original trade-off analysis) that two of the four production runs could be deleted. Lord's management refused, insisting that contractual requirements must be met at the expense of the contractor.

The following week, Elliot Grey called Gary in for an emergency meeting concerning expenditures to date.

Elliot Grey: "Gary, I just received a copy of the financial planning report for last quarter in which you stated that both the cost and performance of the Blue Spider Project were 75 percent complete. I don't think you realize what you've done. The target profit on the program was $200,000. Your memo authorized the vice-president and general manager to book 75 percent of that, or $150,000 for corporate profit spending for stockholders. I was planning on using all $200,000 together with the additional $300,000 I personally requested from corporate headquarters to bail you out. Now I have to go back to the vice-president and general manager and tell them that we've made a mistake and that we'll need an additional $150,000."

Gary Anderson: "Perhaps I should go with you and explain my error. Obviously, I take all responsibility."

Elliot Grey: "No, Gary. It's our error, not yours. I really don't think you want to be around the general manager when he sees red at the bottom of the page. It takes an act of God to get money back once corporate books it as profit. Perhaps you should reconsider project engineering as a career instead of program management. Your performance hasn't exactly been sparkling, you know."

Gary returned to his office quite disappointed. No matter how hard he worked, the bureaucratic red tape of project management seemed to always do him in. But late that afternoon, Gary's disposition improved. Lord Industries called to say that, after consultation with the Army, Parks Corporation would be awarded a sole-source contract for qualification and production of Spartan Missile components using the new longer-life raw materials. Both Lord and the Army felt that the sole-source contract was justified, provided that continued testing showed the same results, since Parks Corporation had all of the technical experience with the new materials.

Gary received a letter of congratulations from corporate headquarters, but no additional pay increase. The grapevine said that a substantial bonus was given to the director of engineering.

During the tenth month, results were coming back from the accelerated aging tests performed on the new materials. The results indicated that although the new materials would meet specifications, the age life would probably be less than five years. These numbers came as a shock to Gary. Gary and Paul Evans had a conference to determine the best strategy to follow.

Gary Anderson: "Well, I guess we're now in the fire instead of the frying pan. Obviously, we can't tell Lord Industries about these tests. We ran them on our own. Could the results be wrong?"

Paul Evans: "Sure, but I doubt it. There's always margin for error when you perform accelerated aging tests on new materials. There can be reactions taking place that we know nothing about. Furthermore, the accelerated aging tests may not even correlate well with actual aging. We must form a company position on this as soon as possible."

Gary Anderson: "I'm not going to tell anyone about this, especially Henry Gable. You and I will handle this. It will be my throat if word of this leaks out. Let's wait until we have the production contract in hand."

Paul Evans: "That's dangerous. This has to be a company position, not a project office position. We had better let them know upstairs."

Gary Anderson: "I can't do that. I'll take all responsibility. Are you with me on this?"

Paul Evans: "I'll go along. I'm sure I can find employment elsewhere when we open Pandora's box. You had better tell the department managers to be quiet also."

Two weeks later, as the program was winding down into the testing for the final verification mix and final report development, Gary received an urgent phone call asking him to report immediately to Henry Gable's office.

Henry Gable: "When this project is over, you're through. You'll never hack it as a program manager, or possibly a good project engineer. We can't run projects around here without honesty and open communications. How the hell do you expect top management to support you when you start censoring bad news to the top? I don't like surprises. I don't like to get the bad news from the program managers and project engineers, most of all not second-hand from the customer. And of course, we cannot forget the cost overrun. Why didn't you take some precautionary measures?"

Gary Anderson: "How could I when you were asking our people to do work such as accelerated aging tests that would be charged to my project and was not part of the program plan? I don't think that I'm totally the blame for what's happened."

Henry Gable: "Gary, I don't think it's necessary to argue the point any further. I'm willing to give you back you old job, in engineering. I hope you didn't lose too many friends while working in program management. Finish up final testing and the program report. Then I'll reassign you."

Gary returned to his office and put his feet up on the desk. "Well," thought Gary, "perhaps I'm better off in engineering. At least I can see my wife and kids once in a while." As Gary began writing the final report, the phone rang:

Functional Manager: "Hello Gary. I just thought I'd call to find out what charge number you want us to use for experimenting with this new procedure to determine accelerated age life."

Gary Anderson: "Don't call me! Call Gable. After all, the Blue Spider Project is his baby."

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

9th Edition

154438419X, 978-1544384191

More Books

Students explore these related General Management questions

Question

Guidelines for Informative Speeches?

Answered: 3 weeks ago