Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the
Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost to cost basis. Dobson began work on a lump-sum contract at the beginning of 2016. As bid, the statistics were as follows:
Lump-sum price (contract price)$4,000,000
Estimated costs
Labor$850,000
Materials and subcontractor1,750,000
Indirect costs400,0003,000,000
$1,000,000
At the end of the first year, the following was the status of the contract:
Billings to date$2,230,000
Costs incurred to date
Labor$464,000
Materials and subcontractor1,098,000
Indirect costs193,0001,755,000
Latest forecast total cost3,000,000
It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date.
Instructions
(a)Compute the percentage of completion on the contract at the end of 2016.
(b)Indicate the amount of gross profit that would be reported on this contract at the end of 2016.
(c)Make the journal entry to record the income (loss) for 2016 on Dobson's books.
(d)Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2016 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,980,000.
(e)Assume the latest forecast on total costs at the end of 2016 was $4,050,000. How much income (loss) would Dobson report for the year 2016?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started