Question
1 Approved Answer
Activity Description ID Start Stop Duration Predecessor Ventura Stadium 1 6/10/2023 6/10/2023 0 N/A Clear Stadium 2 8/2/2023 10/1/2023 60 N/A Demolish Building 3 10/2/2023
Activity Description ID Start Stop Duration Predecessor Ventura Stadium 1 6/10/2023 6/10/2023 0 N/A Clear Stadium 2 8/2/2023 10/1/2023 60 N/A Demolish Building 3 10/2/2023 11/1/2023 30 2 Set up construction site 4 8/1/2023 8/31/2023 30 2 Drive support piling 5 8/1/2023 11/29/2023 120 2 Pour lower concrete bowl 6 8/1/2023 11/29/2023 120 5 Pour main concource 7 4/29/1900 120 4,6 Install playing field 8 3/30/1900 90 4,6 Construct upper steel bowl 9 4/29/1900 120 4,6 Install seats 10 5/19/1900 140 7,9 Build luxury boxes 11 3/30/1900 90 7,9 Install jumbotron 12 1/30/1900 30 7,9 Stadium infrastructure 13 4/29/1900 120 7,9 Construct steel canopy 14 3/15/1900 75 10 Light installation 15 1/30/1900 30 14 Build roof supports 16 3/30/1900 90 6 Construct roof 17 6/28/1900 180 16 Install roof tracks 18 3/30/1900 90 16 Install roof 19 3/30/1900 90 17,18 Inspection 20 8/1/2023 8/21/2023 20 8,11,13,15,19
Activity Description | ID | Start | Stop | Duration | Predecessor | |
Ventura Stadium | 1 | 6/10/2023 | 6/10/2023 | 0 | N/A | |
Clear Stadium | 2 | 8/2/2023 | 10/1/2023 | 60 | N/A | |
Demolish Building | 3 | 10/2/2023 | 11/1/2023 | 30 | 2 | |
Set up construction site | 4 | 8/1/2023 | 8/31/2023 | 30 | 2 | |
Drive support piling | 5 | 8/1/2023 | 11/29/2023 | 120 | 2 | |
Pour lower concrete bowl | 6 | 8/1/2023 | 11/29/2023 | 120 | 5 | |
Pour main concource | 7 | 4/29/1900 | 120 | 4,6 | ||
Install playing field | 8 | 3/30/1900 | 90 | 4,6 | ||
Construct upper steel bowl | 9 | 4/29/1900 | 120 | 4,6 | ||
Install seats | 10 | 5/19/1900 | 140 | 7,9 | ||
Build luxury boxes | 11 | 3/30/1900 | 90 | 7,9 | ||
Install jumbotron | 12 | 1/30/1900 | 30 | 7,9 | ||
Stadium infrastructure | 13 | 4/29/1900 | 120 | 7,9 | ||
Construct steel canopy | 14 | 3/15/1900 | 75 | 10 | ||
Light installation | 15 | 1/30/1900 | 30 | 14 | ||
Build roof supports | 16 | 3/30/1900 | 90 | 6 | ||
Construct roof | 17 | 6/28/1900 | 180 | 16 | ||
Install roof tracks | 18 | 3/30/1900 | 90 | 16 | ||
Install roof | 19 | 3/30/1900 | 90 | 17,18 | ||
Inspection | 20 | 8/1/2023 | 8/21/2023 | 20 | 8,11,13,15,19 |
Enter the task START date based on the predecessor Finish to Start process flow ADD a day to start the next task For duplicate predecessors, use the latest date of the predecessor being used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started