Don't Copy Or Wrong , i will give dislike immediately 3. A construction company has to undertake the construction of a flyover bridge. The work

image text in transcribed

Don't Copy Or Wrong , i will give dislike immediately

3. A construction company has to undertake the construction of a flyover bridge. The work involves a number of activities. Their time estimates and precedence relationship are given in the following table: Activity Preceding activity Time estimates (months) Optimistic Most likely Pessimistic A - 1.522 .5 B A 1.522.5C123 D C 1.522 .5 E B,D 0.511 .5 F E 113 G B,D 33.57HG345 I F,H 1.522 .5 i) Draw the PERT network for the project (1 mark) ii) Find the expected time and variances for each project activity ( 2 marks) iii) Determine the critical path and expected project completion time. What activities need special attention for completion of the project in time? ( 3 marks) iv) If the flyover is completed after 18 months, the contractor will have to pay a penalty of sh 200,000 . What is the probability that the company has to pay the penalty? ( 2 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions