Question: Download and examine the project task list Download project task listfrom the link provided in the module. Based on this task list, you will create
Download and examine the project task list Download project task listfrom the link provided in the module. Based on this task list, you will create a PERT chart and prepare a presentation file that discusses the following: Identify which set of tasks create the critical path. Determine which task would be best to crash (i.e., shorten) the critical path. Determine if there is a change to the critical path by crashing the task. Is there a new critical path? What other information would be
beneficial to know if the selected task was the best option for crashing?
Tasks are in (START) (STOP) formats. So, task AB starts at point A and ends at point B. For tasks BC and BD, they both start when tasks AB ends (point B). Consider this your "dependency" for the project. While most traditional PERT charts have a weighted average, consider the days to complete and crash as the established weighted averages
Step by Step Solution
There are 3 Steps involved in it
To tackle the problem follow these steps to create a PERT chart and analyze the critical path and cr... View full answer