DQuestion 18 4 pts Stripes Inc. has reported the following average operating data for the year. Wait time Process time Inspection time Move time Que
DQuestion 18 4 pts Stripes Inc. has reported the following average operating data for the year. Wait time Process time Inspection time Move time Que time 12 days 7.2 days 0.5 days 0.8 days 3.8 days Rounding to the nearest whole percent, what is the manufacturing cycle efficiency for Stripes Inc.? o 59% ? 51% 30% 98%