Draw a diagram showing the sequence of activities, with arrows indicating dependencies. The length of each arrow can represent the duration of the activity. Creating

Draw a diagram showing the sequence of activities, with arrows indicating dependencies. The length of each arrow can represent the duration of the activity.

Creating a CPM Schedule for a Typical Floor Slab Construction

To create a CPM schedule, you need to identify the sequence of activities and their durations. Here is a step-by-step guide:

  1. Identify the activities and their durations. Based on the given information, here are the activities and their durations:
Activity Duration
Start typical slab cycle 0 days
Button-up and pour wall & column gang forms 0.5 days
Clean and oil gang forms 0.5 days
Cure columns & walls 16 hours
Cure slab & landing 72 hours
Hoist flyforms (table forms - for building slab) 0.5 days
Install duct work for kitchen & bath vents (in slab) 0.5 days
Install electrical conduit in slab 0.25 days
Install slab bottom reinforcing steel 0.5 days
Install slab top reinforcement steel 0.5 days
Install temporary handrails & shore slab below 0.25 days
Install wall and column reinforcing & embedded conduit 0.25 days
Install plumbing and electrical cans (in slab) 0.25 days
Layout & install one side of wall and column gang forms 0.25 days
Layout for slab inserts and embeds 0.25 days
Level flyforms and construct infills (for building slab) 0.25 days
Mount electrical boxes onto gang forms (in columns & walls) 0.25 days
Place and finish slab, and stair landing 1 day
Strip columns and walls (gang forms) 0.25 days
End of typical slab 0 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Property Management

Authors: Mr. Aaron Felix Villaver Paril, Mr. Ariel Reyes Sudario

1st Edition

9798652748937

More Books

Students also viewed these General Management questions