Question
1 Approved Answer
Draw Gantt Chart and calculate the average waiting time for the processes below if they arrive at time 0 (in the order: P3, P4, P1,
Draw Gantt Chart and calculate the average waiting time for the processes below if they arrive at time 0 (in the order: P3, P4, P1, P2) using FCFS (First Come First Served) algorithm. Process P1 P2 P3 Burst Time 3 9 5 P4 7 Draw Gantt Chart and calculate the average waiting time using the given table, using FCFS (First Come First Served) algorithm. Process Burst Arrival Time Time 20 0 P1 P2 12 P3 4 No P4 9