Question

1 Approved Answer

draw the AON diagram; find the critical path and the expected project completion time. Then compute the probability of completing the project in (i) 21

draw the AON diagram; find the critical path and the expected project completion time. Then compute the probability of completing the project in (i) 21 days; (ii) 22 days; and (iii) 25 days.

Expected time (optimistic + 4x monthly + Pessimistic) / 6

Task

a

m

b

Expected

Variance

Std Dev.

A

6.5

7.5

14.5

8.5

1.77

1.33

B

8.5

10.5

12.5

10.5

.45

.67

C

2.5

3.5

4.5

3.5

.11

.33

D

6.5

7.5

8.5

7.5

.11

.33

E

5.5

5.5

9.5

6.2

.45

.67

F

5.5

7.5

9.5

7.5

.45

.67

G

4.5

6.5

8.5

6.5

.45

.67

H

2.5

3.5

3.5

3.3

.03

.17

Activity

Predecessors

Start

None

A

Start

B

Start

C

A

D

A

E

B, C

F

B, C

G

D, E

H

F

End

G, H

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essential SQLAlchemy Mapping Python To Databases

Authors: Myers, Jason Myers

2nd Edition

1491916567, 9781491916568

More Books

Students also viewed these Databases questions

Question

Has the priority order been provided by someone else?

Answered: 1 week ago

Question

Compare the current team to the ideal team.

Answered: 1 week ago

Question

Are the rules readily available?

Answered: 1 week ago