Question
1 Approved Answer
draw the AON diagram; find the critical path and the expected project completion time. Then compute the probability of completing the project in (i) 21
draw the AON diagram; find the critical path and the expected project completion time. Then compute the probability of completing the project in (i) 21 days; (ii) 22 days; and (iii) 25 days.
Expected time (optimistic + 4x monthly + Pessimistic) / 6
Task | a | m | b | Expected | Variance | Std Dev. |
A | 6.5 | 7.5 | 14.5 | 8.5 | 1.77 | 1.33 |
B | 8.5 | 10.5 | 12.5 | 10.5 | .45 | .67 |
C | 2.5 | 3.5 | 4.5 | 3.5 | .11 | .33 |
D | 6.5 | 7.5 | 8.5 | 7.5 | .11 | .33 |
E | 5.5 | 5.5 | 9.5 | 6.2 | .45 | .67 |
F | 5.5 | 7.5 | 9.5 | 7.5 | .45 | .67 |
G | 4.5 | 6.5 | 8.5 | 6.5 | .45 | .67 |
H | 2.5 | 3.5 | 3.5 | 3.3 | .03 | .17 |
Activity | Predecessors |
|
|
Start | None |
A | Start |
B | Start |
C | A |
D | A |
E | B, C |
F | B, C |
G | D, E |
H | F |
End | G, H |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started