Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack. Activity
- Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack.
Activity | Preceding Activity | Time (Weeks) |
A | - | 7 |
B | - | 8 |
C | - | 6 |
D | A | 6 |
E | B | 6 |
F | B | 8 |
G | C | 4 |
H | D,E | 7 |
I | F,G,H | 3 |
2. Do all ES, EF, LS, and LF information for the following network diagram (as shown in the image). Determine the critical path.
3. For the network diagram illustrated as shown in the image. Answer the following questions:
- What is the impact on the end date of the project if activity I slips by three weeks?
- By how many weeks can activity D slip before the end date gets extended?
- If activity A slips by one week, how will the slack in activity G be impacted?
- If activity H can somehow be compressed from seven weeks to two weeks, perhaps by adding a significant number of resources, what will the impact, if any, on the end date of the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started