Question

1 Approved Answer

Draw the network. ( You may use MSP or draw an AOA or AON network by hand. ) Using Excel , calculate the expected time

Draw the network. (You may use MSP or draw an AOA or AON network by hand.)
Using Excel, calculate the expected time (TE) and variance for each activity.
Using the expected times, find the path with the longest expected time. What is the expected time to complete this path? (Use the analytic method.)
Find the probability that the critical path will be completed in 38 days or le

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Methods and Management

Authors: Stephens W. Nunnally

7th edition

135000793, 978-0131716858

More Books

Students also viewed these General Management questions