Draw the project network using the AON approach. Use a START and/or END nodes as needed. Using the normal times and normal costs: Calculate the

  1. Draw the project network using the AON approach. Use a START and/or END nodes as needed.
  2. Using the normal times and normal costs:
  • Calculate the ES, EF, LS and LF of each activity.
  • Calculate and show in the nodes of your AON project network the total slack of the non-critical activities.
  • What is the normal (duration) time of the project? 
  • What are the critical activities and the critical path? 
ActivityPredecessor

Normal time

(days)

A-4
BA9
CB4
DA7
ED4
FD5

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these General Management questions