Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

- Drawings should be neat, and texts should be legible. - Assume saitable data if necessam. 1. Assume that you are the project manager of

image text in transcribed
- Drawings should be neat, and texts should be legible. - Assume saitable data if necessam. 1. Assume that you are the project manager of ABC company that assembles and installs: ATM machines in Bahrain. A new type of ATM machine is to be installed for NBB with a total project cost of BD 50,000 . The engineers have developed an outline of the project with the following activities based on their expertise. Prioritize the requirements of the ATM users for user interfice Design the Layout of the ATM room Select the best software packages for satisfying user requirement functions Order Processors and other hardware items of the ATM machine Order interior decoration items and painting accessorics Customize the different software packages Assemble the ATM machine parts Test the ATM machine hardware assembly Test ATM machine software package Complete the interior work Install the ATM machine Complete the painting Install the ATM Machine software The software part of the project is to be assigned to the Software Project Leader under a condition to utilize only 40% of the total project cost and the Physical part of the project is assigned to a Senior Manager with a limitation to use only 60% of the total project cost. It is mentioned in the contract that only 10% of the total cost is to be utilized for interior of ATM room. The Software project leader has 2 engineers under him: one expert in software programming and the other one good in testing. There are two junior engineers under a Systems Engineer to select and install the hardware components of the ATM machine and an interior design expert to undertake the activities related to the ATM room. (a). Draw the WBS incorporating OBS for the proposed project. ( 15 Marky) (b). Using apportion method estimate the cost (5. Maris) (c). Assuming that you have a contract for 8 units and a total of 1200 labour hours were required for the first unit. Using an improvement rate of 80 , calculate the labour hours per unit and total labour hours required by using learning curve estimates, (10Manks) - Drawings should be neat, and texts should be legible. - Assume saitable data if necessam. 1. Assume that you are the project manager of ABC company that assembles and installs: ATM machines in Bahrain. A new type of ATM machine is to be installed for NBB with a total project cost of BD 50,000 . The engineers have developed an outline of the project with the following activities based on their expertise. Prioritize the requirements of the ATM users for user interfice Design the Layout of the ATM room Select the best software packages for satisfying user requirement functions Order Processors and other hardware items of the ATM machine Order interior decoration items and painting accessorics Customize the different software packages Assemble the ATM machine parts Test the ATM machine hardware assembly Test ATM machine software package Complete the interior work Install the ATM machine Complete the painting Install the ATM Machine software The software part of the project is to be assigned to the Software Project Leader under a condition to utilize only 40% of the total project cost and the Physical part of the project is assigned to a Senior Manager with a limitation to use only 60% of the total project cost. It is mentioned in the contract that only 10% of the total cost is to be utilized for interior of ATM room. The Software project leader has 2 engineers under him: one expert in software programming and the other one good in testing. There are two junior engineers under a Systems Engineer to select and install the hardware components of the ATM machine and an interior design expert to undertake the activities related to the ATM room. (a). Draw the WBS incorporating OBS for the proposed project. ( 15 Marky) (b). Using apportion method estimate the cost (5. Maris) (c). Assuming that you have a contract for 8 units and a total of 1200 labour hours were required for the first unit. Using an improvement rate of 80 , calculate the labour hours per unit and total labour hours required by using learning curve estimates, (10Manks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions