DT Co. produces picture frames. It takes 3 hours of direct labor to produce a frame. DT's standard labor cost is $11.00 per hour. During
DT Co. produces picture frames. It takes 3 hours of direct labor to produce a frame. DT's standard labor cost is $11.00 per hour. During March, DT produced 4,000 frames and used 12,400 hours at a total cost of $133,920. (a) What is DT's labor rate variance for March?