Duck construction is supplying building materials for a new mall construction project in Oregon. Their contract calls for a total of 250,000 tons of material
Duck construction is supplying building materials for a new mall construction project in Oregon. Their contract calls for a total of 250,000 tons of material to be delivered over a three-week period. Duck's supply depot has access to three modes of transportation: a trucking fleet, railway delivery, and air cargo transport. Their contract calls for 120,000 tons delivered by the end of week one, 80% of the total delivered by the end of week two, and the entire amount delivered by the end of week three. Contracts in place with the transportation companies call for at least 45% of the total delivered to be delivered by trucking, at least 40% of the total delivered to be delivered by railway, and up to 15% of the total delivered to be delivered by air cargo. Unfortunately, competing demands limit the availability of each mode of transportation each of the three weeks to the following levels (all in thousands of tons):
Week | Trucking Limits | Railway Limits | Air Cargo Limits |
1 | 45 | 60 | 15 |
2 | 60 | 55 | 10 |
3 | 55 | 45 | 5 |
Costs ($ per 1000 cans) | $200 | $140 | $500 |
The following is the LP model for this problem. The decision variables are shown in cells N52:P54. Cells Q52:Q54 and N55:P55 are functions of the decision variables.
Let Xij = amount shipped by mode i in week j (thousands of tons)
where i = 1(Truck), 2(Rail), 3(Air)
and j = 1, 2, 3
WLij = weekly limit of mode i in week j (as provided in above table, for example WL12 = 60)
MIN: 200(X11 + X12 + X13) + 140(X21 + X22 + X23) + 500(X31 + X32 + X33)
Subject to: Xij WLij for all i and j Weekly limits by mode
X11 + X12 + X13 + X21 + X22 + X23 + X31 + X32 + X33 250 Total required at end of three weeks
X11 + X21 + X31 + X12 + X22 + X32 200 Total required at end of two weeks
X11 + X21 + X31 120 Total required at end of first week
X11 + X12 + X13 0.45*250 Truck mix requirement
X21 + X22 + X23 0.40*250 Rail mix requirement
X31 + X32 + X33 0.15*250 Air mix requirement
Xij 0 for all i and j
The following is a snapshot of the excel worksheet setup for the problem:
Costs | 200 | 140 | 500 | ||
by Truck | by Rail | by Air | Totals | Required | |
Week 1 | 45 | 60 | 15 | 120 | 120 |
Week 2 | 60 | 45 | 0 | 225 | 200 |
Week 3 | 13 | 12 | 0 | 250 | 250 |
Shipped by | 118 | 117 | 15 | ||
Percentage | 0.45 | 0.4 | 0.15 | ||
Total Limit | 112.5 | 100 | 37.5 | ||
Total Cost | $47,480 | ||||
Weekly | Limits | ||||
Truck | Rail | Air | |||
Week 1 | 45 | 60 | 15 | ||
Week 2 | 60 | 55 | 10 | ||
Week 3 | 55 | 45 | 5 |
It should be noted that the above solution is not necessarily feasible, as the problem has not necessarily been solved yet.
For each of the following questions, enter the alphanumeric name for the cell or the range as requested. For example, the cell in column A and row 10 would be entered as A10, and the range from it to cell A14 would be entered as A10:A14 . Use upper case letters to specify cells. DO NOT ENTER THE CELL VALUES (THE NUMERIC VALUES) FOR ANY OF THE FOLLOWING ANSWERS; ENTER THE ALPHANUMERIC CELL NAME USING THE SPECIFIED FORMAT.
What is the objective function cell?
What cell range constitutes the RHS of the "weekly limits by mode" constraints?
What cell constitutes the LHS of the "total required at end of two weeks" constraint?
What cell constitutes the LHS of the "truck mix requirement" constraint?
What cell constitutes the RHS of the "air mix requirement" constraint?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started