Dunder Mifflin Company has the following departmental manufacturing layout for one of its plants: Wait time 10 minutes ------ Casting 12minutes Move and wait time
Dunder Mifflin Company has the following departmental manufacturing layout for one of its plants:
Wait time 10 minutes ------ Casting 12minutes
Move and wait time 15 minutes -------Grinding 6 minutes
Move and wait time 25 minutes ------- Drilling 10 minutes
Move and wait time 20 minutes -------Finishing 2 minutes
A consulting firm has recommended a value stream with the following manufacturing cell:
Casting 12 minutes ---- Grinding 6 minutes -----Drilling 10 minutes ----- Finishing 2 minutes
Required:
1. Calculate the total time it takes to produce a batch of 20 units using the traditional departmental manufacturing layout.
minutes (670)
2. Using cellular manufacturing, how much time is saved producing the same batch of 20 units? minutes
Assuming the cell operates continuously, what is the production rate? units per hour
3. Assume the processing time of Casting is reduced to 9 minutes, while the times of the other processes stay the same. What is the production rate now?
units per hour
How long will it take to produce a batch of 20 units if the cell is in a continuous production mode?
minutes
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started