Duration Normal Activity Crash Crash / days Dependency Cost ($) Time Cost ($) A-Obtain board approval 3 Start 16 2 32 B-Prepare detail plans 14
Duration Normal Activity Crash Crash / days Dependency Cost ($) Time Cost ($) A-Obtain board approval 3 Start 16 2 32 B-Prepare detail plans 14 Start 25 10 36 C- Engage consultants and contractors 7 A 29 4 47 D-Implement project 30 B.C 53 22 77 E- Measure project performance 9 C 18 6 21 F-Assess performance of constructed facilities 3 E 22 2 29 G-Create project report 20 D, E, F 20 16 34