Question

1 Approved Answer

During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.

During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.

2017

2018

2019

Costs incurred to date

$404,000

$853,160

$1,073,000

Estimated costs to complete

606,000

254,840

0

Billings to date

301,000

904,000

1,580,000

Collections to date

271,000

812,000

1,418,000

Instructions:

Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Prepare all necessary journal entries for 2018.

Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And Compliance Audit A Complete Guide

Authors: Gerardus Blokdyk

2020 Edition

0655927727, 978-0655927723

More Books

Students also viewed these Accounting questions

Question

What is the relationship between humans?

Answered: 1 week ago

Question

What is the orientation toward time?

Answered: 1 week ago