During 2017, Pearl Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.

During 2017, Pearl Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.

2017 2018 2019

Costs incurred to date $404,000 - $853,160 - $1,073,000

Estimated costs to complete 606,000 - 254,840 -0-

Billings to date 301,000 - 904,000 - 1,580,000

Collections to date 271,000 - 812,000 - 1,418,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2017

Gross profit recognized in 2018

Gross profit recognized in 2019

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Finance

Authors: Stephen Ross, Randolph Westerfield, Jeffrey Jaffe, Bradford Jordan

12th edition

1259918947, 1260091908, 978-1259918940

Students also viewed these Accounting questions