During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job

During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job was completed on December 15, 2021. For 2021, what amount should Bing recognize as gross profit?

2020 2021
Actual Costs Incurred $405,000 457,000
Estimated Remaining Costs 405,000 0
Billings to Date 360,000 690,000
Collections to Date 200,000 480,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Answer both A and B please

Answered: 1 week ago

Question

2. What is the business value of security and control?

Answered: 1 week ago