Question

1 Approved Answer

During 2021, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2023. The following information is available.

During 2021, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2023. The following information is available.

2021

2022

2023

Costs incurred to date

$404,000

$853,160

$1,073,000

Estimated costs to complete

606,000

254,840

0

Billings to date

301,000

904,000

1,580,000

Collections to date

271,000

812,000

1,418,000

Instructions:

  1. Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
  2. Prepare all necessary journal entries for 2021, 2022, and 2023.
  3. Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Tools for business decision making

Authors: Paul D. Kimmel, Jerry J. Weygandt, Donald E. Kieso

6th Edition

978-1119191674, 047053477X, 111919167X, 978-0470534779

More Books

Students also viewed these Accounting questions