During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do? Check that this information was documented correctly. Meet with the sponsor to ask for their support. Ask the sponsor to close the project and pay the contracted penalty. Check with the team to learn what can be done, and consult an expert