During an earned value management exercise, a project manager is asked by a senior partner about the most current cost estimate. They would like to
During an earned value management exercise, a project manager is asked by a senior partner about the most current cost estimate. They would like to know the value of work completed against actual cost. The best formula to use would be: Question 3 options: EV-PV EV/PV EV-AC EV/AC