During March, the company worked 14,000 machine-hours and produced 8,000 units. The company had originally planned to work 16,000 machine-hours during March. Required: Calculate the
During March, the company worked 14,000 machine-hours and produced 8,000 units. The company had originally planned to work 16,000 machine-hours during March.
Required:
Calculate the activity variances for March.
Utilities | ||
Maintenance | ||
Supplies | ||
indirect labor | ||
Depreciation | ||
Total |
Calculate the spending variances for March.
Utilities | ||
Maintenance | ||
Supplies | ||
Indirect labor | ||
Depreciation | ||
Total |
Cost Formula
utilities $16,200 + $0.18 per machine-hour
Maintenance $38,000 + $1.40 per machine-hour
Supplies $0.40 per machine-hour
Indirect labor $94, 300 + S1.80 per machine-hour
Depreciation 67,700
Actual Cost in March
$20,880
$ 54, 200
5 6,200
$ 124, 000
S 69, 400
Step by Step Solution
★★★★★
3.40 Rating (162 Votes )
There are 3 Steps involved in it
Step: 1
Activity Variances for March 1 Utilities Planned Cost16200 018 16000 hours 22080 Actual Cost20880 Va...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started