During planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to
During planning, the team has identified the items in the following table as work to be done on the project.
Draw a network diagram to graphically depict this flow. All relationships are FS relationships and durations are
in days.
o a ge
A Plan move
B Complete internal constructon to final
floor plan
C Hold kickoff meeting
D Select furniture
E Prepare office for move
F Order new signs
G Set up utilities wiring and so on
H Install new furniturecommunicatons
equipmentcomputers
l Moverelocate
J Close out project
What is the float of Task F Order new signs
ura on ays
e ecessors
Start
c
c
c
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started