During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified. What action should the project manager take? Is Escalate the situation and request approval to move forward. Reassess the design for the two pieces. Confirm the results through a second pilot. Update the assumptions log and assess the risk associated with it
Step by Step Solution
There are 3 Steps involved in it
Step: 1