During the execution phase of the project, you identify a risk that was not previously identified. What will your next step be? Question 18 options:

During the execution phase of the project, you identify a risk that was not previously identified. What will your next step be? Question 18 options: a) Create a workaround b) Ignore it c) Create a response plan d) Note it to the issue log sheet and analyze it