During which procurement processes does procurement negotiation occur? Select one: a. Plan Procurement Management and Close Procurements b. Control Procurements and Close Procurements c. Conduct
During which procurement processes does procurement negotiation occur?
Select one:
a. Plan Procurement Management and Close Procurements
b. Control Procurements and Close Procurements
c. Conduct Procurements and Control Procurements
d. Conduct Procurements and Close Procurements