E9.1 Which is NOT true about the automation project technical specifications? a) It helps in determining which supplier meets the needs of the automation project b) Forces vendors to bid on similar systems c) It explains to the vendors how their systems should work to achieve the desired functionalities a) It forces suppliers to spell out areas where they cannot meet the requirements. E9.2 Which is NOT part of the automation project technical specifications? 460 Modern Distributed Control Systems a) SCOPE b) Functional description c) Testing and Commissioning d) Allocated project budget E9.3] Which is a basic requirement of a DCS system? a) Alarm system b) Plant Optimization c) MES Integration d) Loop Monitoring E9.4 Which is NOT a requirement of the DCS logging functions? a) Hourly log, shift log, Daily log, and monthly log, b) Easy to create customized reports c) Easy to interface using OPC tools d) Provides Loop Monitoring function, e) Comprehensive IT security tools, E9.5 Which is NOT a criterion for vendor capability assessment? a) Corporate viability b) Market share c) Proximity of the head quarter and factories d) Track record E9.6 Which is NOT a criterion for vendor capability assessment? a) Corporate viability b) Market share .) Proximity of the headquarter and factories d) Track record E9.7Which is NOT a criterionfor system 10 capabilities? a) Switching and loop control capabilities b) Number of 10 points per unit e) Scanning period d) Power supply isolation, hackup, and short circuit protection und initsind isolation E9.7 Which is NOT a criterionfor system I/O capabilities? a) Switching and loop control capabilities b) Number of I/O points per unit c) Scanning period d) Power supply isolation, backup, and short circuit protection c) Inputs and outputs ground isolation 59.8| Which is a criterion Control Configuration capability? a) 64 bit embedded processor b) Support of IEC 6113-3 programming languages c) Ability to execute safety and control logio by same controller. d) Allowable Scanning period. E99] Which is NOT a criterion Control Configuration capability? 461 a) Ability to change configuration on-line b) Logic, sequential, or batch functions be configured by the same tool. c) Network redundancy and error detection and correction d) Availability of debugging tools. E9.10 Which is NOT a criterion for networking capability? a) Ability to synchronize time on all controllers b) Network capacity in terms of how many nodes/controllers it can support c) Availability of spare protocols in the network d) Ability to support hardware by other vendors. E9.11| Which is NOT true about Yokogawk ENTUM 3000? a) Up to 256 stations can be connected b) Supports up to 1000,000 tags c) Vnet is a dual redundant 1Gbps open control network d) Vnet links stations such as FCS, HIS, BCV and CGW. 19.12] Which Device can be used to enable applications to access CENTUM 3000 data? a) GSOW b) APCS c) CGW d) Exaope E9.13 Which device can be used to enable CENTUM 3000 to access data from other subsystems? a) GSGW b) APCS c) CGW d) E9.14) Which device can be used to link Vnet to Ethernet? a) GSGW b) Layer 2 switch c) CGW d) BCV E9.15) Which Device can be used to link Vnct to another Vnet domain? a) GSGW b) Layer 2 switch c) CGW d) BCV 19.16 Which Device executes the basic control functions? a) APCS b) FCS 462 Modern Distributed Control Systems c) HIS d) FIO E9.17) In Honeywell Experion system, which is not an option for execution of control functions? a) ACE station software b) HMI console c) C200/C300 d) PMD controller E9.18) In Honeywell Experion system, which ihn an option for execution of control functions? a) SCE b) Third party controller c) FFB device d) PMD controller E9.19 l Honeywell Experion system, which is not a function of ControlNet? a) Controller-to-I/O communications b) Controller-to-Controller communications c) Third party controllers to Experion HMI d) Controller to Server communications 19.20 In Honeywell Experion system, which is not a function of FTE network a) Controller-to-I/O communications b) Controllerto-Controller communications c) Controllers to displays and HMI d) Controller-to-Server communications E9.211 In Honeywell Experion system, which is not a festure of C300 controller? *) Ability for fast execution cycle (20 msec.) b) Support redundant configurations c) Up to 64 10 units d) Can act as an Application Control Environment e) Interface to Field buses E9.22] In Honeywell Experion system, which module executes the control strategy? a) PKS b) 10 modules c) CPM d) FIM e) C200 E9.23] Which is not a feature of Siemens PCS 7 AS RTX system? a) Control strategy can run on any PC with Windows operating system b) Ideally suited for distributed installation on a factory floor 463 c) Scalable for large distributed structures using ET 200 with PROFIBus interfaces d) Uses Ethernet 10/1000 Mbps. E9.24) Which is not a feature of Siemens S7-400 bused automation systems? a) 87.400 is a powerful and highly reliable IXS controller b) Modular and fan less structure, high expandability, long-term availability, and extensive communication options c) Support of large structures of inpubbhutputs using ET 200 d) Fast operating machines via PROFIBUS