Each of activities E and F require 4 masons / day . The maximum availability of masons is 4 per day. If the late start
Each of activities and require masonsday The maximum availability of masons is per day. If the late start LS date of activity is day and the late start LS date of activity F is day Which activity should be scheduled first?
E
F
Both can be scheduled to be completed simultaneously at the same time