Each of activities E and F require 4 masons / day . The maximum availability of masons is 4 per day. If the late start
Each of activities E and F require masonsday The maximum availability of masons is per day. If the late start LS date of activity E is day and the late start LS date of activity F is day Which activity should be scheduled first?