Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: - Production plans for complete kits are as follows: Start assembling 5,000 kits in week 2 Start assembling 8,000 kits in weeks 3,4 , and 5 Start assembling 20,000 kits in week 6 - The gross requirements for the system unit have already been given to you. For the remaining items, you will nee to figure out the gross requirements. - All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). More Info System unit: Lead Time =1 week; Minimum order quantity =19,000 \begin{tabular}{lcccccc} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requirements & & 5,000 & 8,000 & 8,000 & 8,000 & 20,000 \end{tabular} Scheduled receipts Projected ending inventory: 8,000 Net requirements Planned receipts Planned orders Speakers: Lead Time =1 week; Minimum order quantity =13,000 \begin{tabular}{|c|c|c|c|c|c|c|} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requirements & & & & & & \\ \hline Scheduled receipts & 1,500 & & & & & \\ \hline Projected ending inventory: 5,000 & & & & & & \\ \hline Net requirements & & & & & & \\ \hline Planned receipts & & & & & & \\ \hline Planned orders & & & & & & \\ \hline CD-ROM drivers: Lead Time =2W & Minim & order & ntity & & & \\ \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \end{tabular} Print Done Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: - Production plans for complete kits are as follows: Start assembling 5,000 kits in week 2 Start assembling 8,000 kits in weeks 3,4 , and 5 Start assembling 20,000 kits in week 6 - The gross requirements for the system unit have already been given to you. For the remaining items, you will nee to figure out the gross requirements. - All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). More Info System unit: Lead Time =1 week; Minimum order quantity =19,000 \begin{tabular}{lcccccc} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requirements & & 5,000 & 8,000 & 8,000 & 8,000 & 20,000 \end{tabular} Scheduled receipts Projected ending inventory: 8,000 Net requirements Planned receipts Planned orders Speakers: Lead Time =1 week; Minimum order quantity =13,000 \begin{tabular}{|c|c|c|c|c|c|c|} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requirements & & & & & & \\ \hline Scheduled receipts & 1,500 & & & & & \\ \hline Projected ending inventory: 5,000 & & & & & & \\ \hline Net requirements & & & & & & \\ \hline Planned receipts & & & & & & \\ \hline Planned orders & & & & & & \\ \hline CD-ROM drivers: Lead Time =2W & Minim & order & ntity & & & \\ \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \end{tabular} Print Done